Corporate Presentation
Released
Released
Announcement PDF
Fuelling the Future
ASX:BRU
Example of a small-scale LNG facility at Mount Magnet, Western Australia.
Photo courtesy of Clean Energy Fuels Australia (CEFA)
Material Value Build + Energy Security
for
Northwest of Western Australia
June 2026
ASX: BRU
Disclaimer
This document has been prepared by Buru Energy Limited ABN 71 130 651 437 (“Buru”) and has been authorised for the intended purpose by the Executive Chair of Buru Energy Limited.
This presentation contains certain statements which may constitute "forward-looking statements". It is believed that the expectations reflected in these statements are reasonable but they may be affected
by a variety of variables and changes in underlying assumptions which could cause actual results or trends to differ materially, including, but not limited to: price fluctuations, actual demand, currency
fluctuations, drilling and production results, reserve and resource estimates, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal and regulatory developments,
economic and financial market conditions in various countries and regions, political risks, project delays or advancements, approvals and cost estimates. All of Buru’s operations and activities are subject to
joint venture, regulatory and other approvals and their timing and order may also be affected by weather, availability of equipment and materials and land access arrangements, including native title
arrangements. Although Buru believes that the expectations raised in this presentation are reasonable there can be no certainty that the events or operations described in this presentation will occur in the
timeframe or order presented or at all.
There are numerous uncertainties inherent in estimating reserves and resources, and in projecting future production, development expenditures, operating expenses and cash flows. Oil and gas reserve
engineering and resource assessment must be recognised as a subjective process of estimating subsurface accumulations of oil and gas that cannot be measured in an exact way. All contingent resources
and prospective resources presented in this report are pursuant to the Company’s ASX releases of 14 August 2025, 26 July 2024, 17 June 2024 and 18 January 2018 . The estimates of contingent and
prospective resources included in this Presentation have been prepared in accordance with the definitions and guidelines set forth in the SPE PRMS. Buru is not aware of any new information or data that
materially affects the information included in this presentation and all material assumptions and technical parameters underpinning the estimates in this presentation continue to apply and have not
materially changed. The probabilistic method was used to prepare the estimates of the contingent and prospective resources.
No representation or warranty, expressed or implied, is made by Buru or any other person that the material contained in this presentation will be achieved or prove to be correct. Except for statutory liability
which cannot be excluded, each of Buru, its officers, employees and advisers expressly disclaims any responsibility for the accuracy or completeness of the material contained in this presentation and
excludes all liability whatsoever (including in negligence) for any loss or damage which may be suffered by any person as a consequence if any information in this presentation or any error or omission
there from. Neither Buru nor any other person accepts any responsibility to update any person regarding any inaccuracy, omission or change in information in this presentation or any other information
made available to a person nor any obligation to furnish the person with any further information.
All references to $ are in Australian currency, unless stated otherwise.
Company snapshot
Rafael Gas Project, Canning Basin, WA
Rafael - the core and primary focus
Buru 100% and Operator
Conventional gas & liquids (diesel & LPG)
Foundation based on P90 delivers material
long-term cashflows from 2028/early 2029
Significant upside P50/P10 Resource and
exploration (Flying Fox)
Other assets, Canning Basin, WA
Ungani oil – assessing operational and
market options
Mars - high value oil prospect
Yulleroo – significant gas & liquids resource
Where We Operate
1
Board of Directors
Ms Joanne Williams
Executive Director 4
Mr Malcolm King
Independent Non-Executive Director
Mr David Maxwell
Executive Chair 4
Buru Energy | Fuelling the Future - June 2026
Capital Structure
Shares on issue1 million 1,354
Market Capitalisation1 A$ million 17.6
Cash1 A$ million 5.0
Debt A$ million Nil
12-month high cents/share 3.6
12-month low cents/share 1.2
Shareholders by Type3 Research
1 as at 4 June 2026,
3 as at 31 December 2025.
82.0%
16.51%
0.5% 1.0%
Retail & HNW
Domestic
Institutions
Foreign
Institutions
Directors &
Employees
4 Executive Directive since 8 May 2026. Refer ASX announcement of 1 April 2026
Building robust long term cash flow foundation with growth.
Rafael Gas Project summary
2
High value gas
& liquids
(diesel & LPG)
business
Rafael Gas Project has no competition as a regional producer of gas, diesel & LPGs.
Attractive returns and long-term (~20 years) foundation cash flow from 2028/29.
…based on
proven
resource (P90)
Rafael discovery in 2021, the first proven major conventional gas field found onshore in the
Canning Basin, Western Australia (WA). Buru owns 100% and operates the field.
Foundation Project based on high confidence (P90) resource volume of 85 Bscf gas and
1.8 MMstb liquids.
Significant resource upside via P50 (best estimate), P10 (high estimate) + deeper resource play
(Flying Fox).
… developed
via a simple
project
Small footprint based on existing well pad and modularised 250-300tpd LNG plant:
- proven design, with existing plants in WA, and
- initial 2 wells (including the discovery well)
… to supply an
existing market
with growth
Local source of LNG & liquids (diesel & LPG)
Replacing costly and insecure long-distance trucking or imported fuel
… with an
established
downstream
partner
Business model with Clean Energy Fuels Australia (CEFA) to finance, build, own and operate
LNG plant.
Model includes CEFA investment of ~ A$150 million (80% of project capex) recovered via a fee
payable by Buru.
Buru pre-FID spend limited to 2 production wells, approvals and upstream operations
… being
optimised to
maximize
shareholder
value
Liquids (diesel & LPGs) adds significant project value
Short payback and attractive economic returns
Rafael 1 well testing – March 2022
Buru Energy | Fuelling the Future - June 2026
Valuable energy resilience
Rafael Gas Project – competitive advantages
The regional energy solution
1Diesel imported via Broome, Wyndham or trucked from Perth. LPGs trucked from Perth or Darwin
2Regional gas generators are fuelled by LNG delivered by road from Karratha. This is costed at $22/GJ.
(Broome Clean Energy Study Feb 2023, Sustainable Energy Now)
Proximity to market
Delivered cost
Transport emissions
Regional development
New market opportunities
Synergy with renewables
Existing trucked / imported
gas, diesel & LPG
Rafael Gas
Project
615 - 1,520+ km1 70 – 685 km
Project Benefits
2
CO2
CO2
Buru Energy | Fuelling the Future - June 2026
3
Rafael – high value foundation
Economic Screening1 based on Rafael 1C Resource (P90), 12-month production ramp up, and
production rates of 200 tpd LNG, 69 kLpd diesel (and other associated liquids) and 15tpd LPG for 20
years. Assumes 100% Project Economics and “mid-case” LNG, condensate (diesel and other
associated liquids) and LPG sales price assumptions.
Economic screening date 2026 2026
Financial structure Capex Model2 Opex Model3
Gas Sales Price A$/GJ (domestic)4 $15.00 $15.00
Average Liquids Sales Price A$/litre (domestic) $1.50 $1.50
LPG Sales Price A$/tonne (domestic) $900.00 $900.00
Following in gross terms (A$), 2026$, pre-tax
Total gas revenue ($million) 1,810 1,810
Total diesel (and other associated liquids) revenue ($million) 910 910
Total LPG revenue ($million) 120 120
Total Opex/Royalties ($million) (790) (1,160)
Average Pre-Tax Operating Cashflow/annum ($million) 103 84
NPV10 ($million) 590 560
IRR 42% 80%
1 Equity economics, ungeared in 2026-dollars. Basis of project design include a 3rd well in Year 8 and capex for liquids separation, stabilisation and storage. The figures are before any financing costs and inclusive of facilities and well capex and provisions
for abex. NPV and IRR are pre-tax. Buru Energy has more than $200 million in tax losses which can be applied against future profits.
2 Capex model – 100% equity to finance entire project development, vs pay a recurring service fee (tariff) to a third party.
3 Opex model - third party capex plant investment (e.g. CEFA) recovered through a tariff
4 Regional gas fired power stations are fuelled by LNG delivered over long distances (615 – 1,520kms). This is costed at $22/GJ (Broome Clean Energy Study Feb 2023, Sustainable Energy Now)
4
Key insights
Rafael has significant project value
42 – 80% IRR depending on commercial model
based on P90 Resource alone
Average cashflow pre-tax/year more than 3 x BRU
market cap
Diesel & LPG adds material value
Robust long term foundation cash flow
Material low-cost growth opportunities
- 200 tpd LNG c.f. 250-300 tpd plant capacity
- P50 Resource = 2.5 x P90 Resource
- Flying Fox exploration opportunity
Rafael Contingent Resources – T20 primary reservoir
Interval only (Buru analysis, post Rafael 3D seismic survey, pre-inversion analysis)
Gross 1C2 2C 3C
Gas (Bscf) 85 220 523
Condensate (MMstb) 1.8 4.5 10.6
Nett 1C2 2C 3C
Gas (Bscf) 76 176 401
Condensate (MMstb) 1.6 3.6 8.1
1Refer to the ASX release of 26 July 2024 for full definitions and disclosures. Buru is
not aware of any new information or data that materially affects this assessment and
that all material assumptions and technical parameters underpinning the estimates
continue to apply and have not materially changed.
2High confidence resource volumes used to underpin Rafael Gas Project basis
Rafael 1 drilled on 2D seismic in 2021 encountered significant
gas columns in a large 4-way structural closure.
(1) Primary Reservoir Interval (robust base case):
Crestal T20 Ungani Dolomite (Contingent Resources)
Proven reservoir, produced in Ungani Oilfield
Flow tested in 2022 and produced at 7.6 MMscf/d
(2) Secondary Reservoir Interval (upside):
Upper T30 Laurel Dolomite (Prospective Resources)
Petrophysical evaluation indicates gas
Interval could not be tested in Rafael 1 due to operational difficulties
Rafael – large high confidence onshore resource
Ungani Dolomite Depth Structure Map
Rafael 1 (2021)
Rafael 2 (Proposed)
Depth
(mTVDSS)
5
Buru Energy | Fuelling the Future - June 2026
Rafael – resource distribution
Rafael 1 (2021)
Rafael 2 (Proposed)
Ungani Dolomite Depth Structure Map
Depth
(mTVDSS)
Rafael 1 Fault Block
Rafael 1 drilled in late 2021
Rafael 1 production tested in 2022
3D seismic acquired in 2023
Rafael 1 fault block only
analysis underway
- very encouraging preliminary
results
Maybe economic based on Rafael
1 fault block only
6
Buru Energy | Fuelling the Future - June 2026
Flying Fox Prospective Resources1 (Buru analysis, post Rafael 3D seismic survey)
1 Prospective Resources relate to the estimated quantities of petroleum that may potentially be recovered by the application of a future development
project(s) relate to undiscovered accumulations. These estimates have both an associated risk of discovery and a risk of development. Further
exploration appraisal and evaluation is required to determine the existence of a significant quantity of potentially moveable hydrocarbons.
Please refer to ASX Release of 14 August 2025 for full definitions and disclosures. Buru is not aware of any new information or data that materially
affects this assessment and that all material assumptions and technical parameters underpinning the estimates continue to apply and have not
materially changed.
Flying Fox – prospect beneath Rafael
Prospect: Devonian carbonate target, imaged on recently acquired Rafael 3D,
immediately beneath the Rafael 1 discovery, within a faulted closure of 26 km2 and
~370m vertical relief
Opportunity: upside Prospective Resource for the Rafael development
Could be tested by incremental deepening of proposed Rafael 2H well by ~ 500m
Primary Target: gas reservoir in dolomitized, vuggy, reef facies of the Nullara or
Pillara Fm (Devonian) and sealed by shales of the May River Formation
Chance Of Success: 45%
Key risks and uncertainties:
• Reservoir quality – effectiveness risk for the dolomitized Devonian carbonate
• Fault seal – risk to leak into overlying T20 Ungani Dolomite
7
Flying Fox - potential significant resource upside
Chance of
Success
Condensate (MMstb) Gas (Bscf)
(COS %) 1U 2U 3U 1U 2U 3U
Gross Prospective Resources 45 1.2 5.0 12.6 60 247 614
Net Prospective Resources 45 1.1 4.6 11.3 57 226 551
A’
A
Rafael 1
Proposed
Rafael B
Buru Energy | Fuelling the Future - June 2026
Capital efficient project design
Based on high confidence 1C Resource of 85 Bscf
2C best estimate (220 Bscf) or the 3C resource case (523 Bscf)1
adds material upside
Small footprint, based around the existing cleared Rafael 1
discovery well pad – enabling simple and fast project approvals
No pipeline - trucked LNG, diesel, LPG & other associated liquids
Proven design, modularised construction
Many global small scale LNG plants in operation, with several in
Australia (and WA)
Production - up to 300t/day of LNG with associated liquids
(diesel and LPG etc)
Development plan based on 2 wells (including the recompletion of
the Rafael 1 discovery well as a production well)
Approx 20-year production life with robust cashflow
Significant upside with greater resource and market growth
Indicative well locations for
Rafael 1 (existing discovery well)
and Rafael 2H (previously B)
(planned new well for drilling in
2027) 1 Refer to the ASX release of 26 July 2024 for full definitions and disclosures.Buru is not aware of any new information or data
that materially affects this assessment and that all material assumptions and technical parameters underpinning the
estimates continue to apply and have not materially changed.
8
Buru Energy | Fuelling the Future - June 2026
LNG and liquids plant – proven design
9
SMR process - workhorse
of LNG industry used in many
liquefaction installations
Working to ensure:
- strategic and competitive value
is realised
- funding structure reflects the
gas, diesel, LPG & associated
liquids value
- Buru value uplift benefits are
realised
Rafael Gas Project
Generic Single Mixed Refrigerant (SMR) based Small Scale Process Scheme
LPG - to compete with
existing high-cost
imported supply
Liquids/diesel - to
compete with existing
high-cost supply and/or
export
LNG - value
reconfirmed from
process flow
modelling
Feedstock for
power generation,
minerals
processing, marine
and transport
Buru Energy | Fuelling the Future - June 2026
Units
Economics
Basis
Plant
Capacity
LNG tonnes/day 200 300
Diesel & assoc.
liquids
kilolitres/day 69 103
LPG tonnes/day 15 22
Rafael location delivers regional supply advantage
10
Horizon Power Service Area, Horizon Power Annual Report 2024
Existing gas fired power stations
Rafael
Horizon Power (WA government-owned entity) - responsible for
generating, procuring, distributing, and selling electricity in region.
Horizon Power - currently executing the West Kimberley Power Project
(WKPP) designed to solve the Kimberley's heavy and expensive
reliance on diesel for electricity with a new system expected to deliver
in the 2028 – 2030 window.
Annual power consumption of the 5 main Kimberley demand centres
(Broome, Derby, Camballin/Looma, Fitzroy Crossing and Halls Creek)
is ~ 190 GWh1 excluding power consumption for mining use.
Current gas demand for retail power generation is 6TJ/d to 13TJ/d
(seasonal).
Plus more than 100 remote communities rely on diesel for primary
power generation.
Additional robust demand for power outside the immediate “capture
zone” by resource projects not on the gas pipeline network.
Existing and probable local mine project demand estimated at >15TJ/d.
1 Published Horizon Power data
Buru Energy | Fuelling the Future - June 2026
Rafael growth offtake opportunities
11
Project Owner Location Road distance
from Karratha
(kms)
Road distance
from Rafael
(kms)
Approx.
daily
demand
Notes
Thunderbird Mineral Sands mine Sheffield Resources /
Yansteel
West Kimberley 730 115 2 TJ/d Natural potential customer due to proximity to Rafael
Kimberley Meat Works Alberta Investment
Management Co.
West Kimberley 845 70 0.5 – 1 TJ/d Natural potential customer due to proximity
Browns Range Heavy Rare
Earths mine
Northern Mineral East Kimberley 1,545 710 2 TJ/d FID 2Q 2026. First ore 2028. Requires trucked LNG
Savannah Project Zeta Resources East Kimberley 1,405 570 3-4 TJ/d Currently under Care & Maintenance , proposal to
create consolidated regional processing facility
Winu Copper/Gold/Silver mine Rio Tinto North Pilbara 615 620 3 TJ/d FID early 2027. First ore 2030. Requires trucked LNG.
Rafael location very competitive.
Speewah Fluorite and Vanadium
Projects
Tivan Limited East Kimberley 1,520 685 1.5 – 3 TJ/d FID 4Q 2026. First ore 2029. Local offtake.
Ridges Iron Ore Project Kimberley Metals
Group (KMG)
East Kimberley N/A 630 0.3 – 0.5 TJ/d Currently reliant on diesel for both plant power and
heavy mobility fuel.
Curtin Airbase Department of
Defence
West Kimberley N/A 90 Variable Opportunity for diesel and LPG
Power generation for remote
communities
Horizon Power Various >1,000 >100 Variable Opportunity for diesel and LPG
Transport & marine supply Wholesale & retail
markets
Kimberley / Pilbara N/A >100 4 to 6 million
litres
Diesel opportunity
LPG supply Wholesale & retail
markets
Kimberley / Pilbara N/A >100 25 to 50
tonnes
LPG opportunity
Buru Energy | Fuelling the Future - June 2026
Derisked funding through strategic partnership
A renewables and thermal hybrid
power company powering the
next generation of mining and
resource projects in Australia.
Delivers LNG with an extensive
range of LNG sources and
distribution capabilities, including:
CEFA’s 250 tpd plant in Mt
Magnet, and it’s lifting
agreements at the 175tpd LNG
plant in Kwinana and 400tpd
Pluto LNG truck loader in
Karratha, WA
Australia’s largest fleet of LNG
road tankers and ISO containers
LNG storage and vaporisation
facilities for power generation
and industrial applications
across Australia
Builds, owns and operates
integrated LNG solutions for
mining operations,
communities and industry in
Australia, with a strong
portfolio of West Australian
customers including
Westgold Resources, Vault
Minerals, Lynas Rare Earths,
Pilbara Minerals and
Bellevue Gold.
An energy focused portfolio company, investing in energy infrastructure and low-carbon solutions
US private equity firm with US$40 billion in assets under management. Investments in 89 companies operating
across 70+ countries. The company invests in energy, utilities, transport and telecommunication projects in
North America, Europe, Asia and Latin America.
12
CEFA (downstream operator) -
finance, build, own and
operate Rafael Gas Plant and
distribute LNG to market
(~A$ 150 million)
Buru (upstream
operator) - drill low-
risk well (Rafael 2H)
to support Reserves
Certification and flow-
assurance and
convert Rafael 1 well
to production well.
Buru pays a fee to CEFA to process
and distribute gas to customers
Co-operation on marketing
to be determined
Buru Energy | Fuelling the Future - June 2026
Optimised schedule to capture value pre-FID
13
First cashflow targeting late 2028 / early 2029
Value-add activities:
1. Upstream / downstream project
integration
2. Gas, liquids (diesel and LPG) marketing
3. Upstream funding, project commercial
frameworks and agreements
4. EPA2 WA Referral
5. Agreement making with Traditional
Owners
6. Drilling and flow testing Rafael 2H,
recompleting and flow testing Rafael 1
7. Reserves Certification
1LPG = Liquified Petroleum Gas.
2EPA = Environmental Protection Authority Western Australia
Drill Rafael 2H and Rafael 1 recompletion post-wet season, de-risks operational logistics, rig availability and aligns with the optimised development plan.
Buru Energy | Fuelling the Future - June 2026
Buru funding options being assessed
14
Buru is working with Carlingford (UK) to facilitate the funding process with potential counterparties and others
Several options being pursued in parallel
Status of
partner
engagement
Multiple parties entering the Data Room and conducting technical and
commercial due diligence.
Range of options available and under review
Strong project
fundamentals
Attractive project economics and improving sentiment on the role of gas,
diesel and LPG in the medium to long term as reasons for interest
~20 years foundation production and cash flow
Robust foundation project with material upside opportunities
Process
ongoing
Local and international parties whose strategic horizons remain aligned with
project and value realisation timing.
Liquids (diesel and LPG) product streams create additional
project value, which increases the options available for funding
and commercial agreements
Buru Energy | Fuelling the Future - June 2026
PE/VC who
specialise in the
energy sector
provide capital
needed for
resource appraisal
Partnering with
other companies
to share upstream
risk / reward
associated with
the Rafael Gas
Project
Loans / convertible
notes secured
against Rafael asset
or future production
Collaborate with
larger, established
companies to
provide funding in
exchange for
share in future
profits or
production
Buru has a portfolio of assets - Ungani oilfield (100%)
15
Ungani under care and maintenance since
August 2023
Produced ~2.3MMbbls of oil to date with
~220,000 bbls remaining
Oil was previously sold at a premium to Dated
Brent into the Southeast Asian market
Evaluating Ungani restart scenarios
Success at nearfield exploration prospect (Mars)
can underpin re-commencement of production
with robust economics
Currently seeking expressions of interest for the
drilling of the Mars 1 exploration well
Buru Energy | Fuelling the Future - June 2026
Buru has a portfolio of assets – Mars prospect (100%)
Located 9km from the Ungani Production Facility (UPF),
Mars 1 discovery can underpin UPF restart and increase
commercialisation options on robust economic terms
Pipeline solution to Ungani could be laid in ~ 20 days at a cost of
A$2 million
40% Geological Chance of Success
Mars 1 exploration well planned maximum total vertical depth of
1,808 mTVDSS (success case)
Drill and complete cost ~A$7 million
Progressing discussions with third parties
1 Prospective Resources relate to the estimated quantities of petroleum that may
potentially be recovered by the application of a future development project(s)
and relate to undiscovered accumulations. These estimates have both an
associated risk of discovery and a risk of development. Further exploration,
appraisal and evaluation is required to determine the existence of a significant
quantity of potentially moveable hydrocarbons. Refer to Buru ASX Release 17
June 2024 for full definitions and disclosures. Buru is not aware of any new
information or data that materially affects this assessment and that all material
assumptions and technical parameters underpinning the estimates continue to
apply and have not materially changed.
Prospective Resources (MMbbls)1 Low Best High
Stock Tank Oil Initially in Place (STOIIP) 3.0 10.6 21.7
Ultimate Recovery of Oil (UR) 0.7 2.8 6.2
16
Buru Energy | Fuelling the Future - June 2026
Buru has a portfolio of assets – Yulleroo (100%)
Depth Structure Map of the near top Lower Laurel Carbonates
Yulleroo 2 clean-up flow 2010
Prospective Resources Low Best High
Sales Gas (PJ) 124.6 302.8 611.0
Associated Liquids (MMbbls) 4.3 11.9 24.8
Yulleroo accumulation is defined by four wells - all intersecting thick gas saturated sections with
gas below closure mapped on 3D seismic and Yulleroo 4 deliberately drilled outside closure
Potential conventional pay in Yulleroo 3
Yulleroo 2 in 2010 (3 zones) produced rates up to 1.8 mmcfd and high condensate content
Independent review by RISC estimated Contingent and Prospective Resource sales gas and
associated liquids in the Yulleroo Field as at 1 December 2017 as follows:
Contingent Resources 1C 2C 3C
Unlimited Recoverable Sales Gas (PJ) 321.4 714.0 1,627.0
Unlimited Recoverable Associated Liquids (MMbbls) 9.5 24.9 47.6
• RISC’s Contingent Resource and Prospective Resource assessment has been prepared using the probabilistic method and an evaluation date of 1 December 2017.
• Contingent Resources are quantities of petroleum estimates as of a given date to be potentially recoverable from known accumulations by application of development project(s) but which are not
currently considered to be commercially recoverable due to one or more contingencies. Contingent Resources are a class of discovered recoverable resources.
• Prospective Resources are estimated quantities of petroleum that may potentially be recovered by the application of a future development project(s) that relate to undiscovered accumulations. These
estimates have both an associated risk of discovery and a risk of development. Further exploration, appraisal and evaluation is required to determine the existence of a significant quantity of
potentially moveable hydrocarbons.
• The full resource statement is set out in accordance with ASX Listing Rules in Buru’s ASX release of 18 January 2018. Buru Energy is not aware of any new information or data that materially affects
the information included in the 18 January 2018 release and all material assumptions and technical parameters underpinning the estimates in that release continue to apply and have not materially
changed.
A significant unconventional gas and liquids rich accumulation on the western side of the Canning Basin
17
Summary
Rafael Gas Project transforms Buru
- material foundation long term cash flow within 2 to 3 years
- base case on P90 resource
- valuable competitive advantages
- high value upside opportunities
Partnering with CEFA
- an existing growing industry participant
- build own and operate processing plant
Rafael funding, securing project approvals and commercial agreements are the key near term deliverables
Advancing work to capture value from the other main assets
- Ungani and Mars – oil
- Yulleroo - gas
Buru Energy | Fuelling the Future - June 2026
18
Experienced team to deliver
19
Ms Joanne Williams
Executive Director from 8 May 20261
>25yrs technical, engineering
Mr Malcolm King
Independent Non-Executive Director
>35yrs commercial, exploration, operations
Paul Bird
CFO and Company Secretary
>25yrs finance, governance
Mr David Maxwell
Executive Chair from 8 May 20261
>35yrs strategy, gas commercialisation, risk and asset management
Leaders with deep industry
experience and a track
record of value delivery
Project
Development
Support
Buru Energy | Fuelling the Future - June 2026 1 Executive Directive since 8 May 2026. Refer ASX announcement of 1 April 2026
Back-up
ASX:BRU
Example of a small-scale LNG facility at Mount Magnet, Western Australia.
Photo courtesy of Clean Energy Fuels Australia (CEFA)
Rafael Contingent Resources1 – T20 primary reservoir
interval only (Buru analysis, post Rafael 3D seismic survey, pre-inversion
analysis)
Gross 1C2 2C 3C
Gas Bscf 85 220 523
Condensate MMstb 1.8 4.5 10.6
Net 1C2 2C 3C
Gas Bscf 76 176 401
Condensate MMstb 1.6 3.6 8.1
1 Refer to the ASX release of 26 July 2024 for full definitions and
disclosures. Buru is not aware of any new information or data that
materially affects this assessment and that all material assumptions
and technical parameters underpinning the estimates continue to
apply and have not materially changed.
2 High confidence resource volumes used to underpin Rafael Gas
Project basis
Rafael 1 drilled on 2D seismic in 2021 encountered
significant gas columns in a large 4-way structural closure.
(1) Primary Reservoir Interval (robust base case):
• Crestal T20 Ungani Dolomite (Contingent Resources)
• Proven reservoir, produced in Ungani Oilfield
• Flow tested in 2022 and produced at 7.6 MMscf/d
(2) Secondary Reservoir Interval (upside):
• Upper T30 Laurel Dolomite (Prospective Resources)
• Petrophysical evaluation indicates gas
• Interval closed off and was not tested in 2022 due to operational difficulties
Rafael - a large, onshore high confidence resource
Rafael 1
Drilled
W E
Depth
(mSS)
Carbonate
Indicator
Ungani Dolomite T20
Upper Laurel Dolomite T30
T20 Ungani Dolomite
TESTED INTERVAL
T30 Upper Laurel Dolomite
UNTESTED ZONE
Rafael Web-AVO Inversion – K Bulk Modulus, Carbonate Indicator
Rafael 2H
planned
for early
2027
Deeper Nullara Carbonate
Buru Energy | Fuelling the Future - June 2026
21
Buru Energy Limited
Level 2, 16 Ord Street
West Perth, Western Australia 6005
PO Box 1903
West Perth WA 6872
Email: info@buruenergy.com
Phone: 1800 337 330
Website: www.buruenergy.com
ASX:BRU
David Maxwell – Chair
Paul Bird – CFO
Share your feedback
Discover