Quarterly Activities and Cash Flow Report - Dec 2023
Released
Released
Announcement PDF
Quarterly Report
Period ended 31 December 2023
Buru Energy Limited (Buru, Company) is pleased to provide the quarterly report for the period
ended 31 December 2023.
Chief Executive Officer’s comments on the report:
“Buru finished the 2023 calendar year in a robust position against its strategic plan, creating a
platform for growth and value creation across its portfolio of assets.
ASX:
BRUhas seen Buru regain full ownership of Rafael, the first significant conventional gas
The year
and condensate discovery in the onshore Canning Basin of Western Australia.
Commercialising the Rafael resource is Buru’s priority, and the year has seen material progress
achieved in support of this endeavor.
Key milestones delivered included the completion of a 3D seismic survey over the Rafael
structure; the commitment to long lead well equipment in support of planned appraisal drilling
in 2024; the commencement of pre-FEED engineering for a Phase 1 Rafael development, and
the commencement of a strategic appraisal/development partner selection process for the
asset.
These activities are designed to drive the certainty of outcome for a Rafael development, with
the potential to transform Buru from an explorer to a developer and producer of natural gas
during a period of projected supply shortfalls in the domestic market in Western Australia and
increased global demand internationally.
The year has also seen Buru regain full ownership of the Ungani oilfield and associated
production infrastructure. Although production operations are currently suspended, Buru is
actively investigating opportunities to extract maximum value from this asset.
Although the lion’s share of the Company’s resources and capital is allocated to the
commercialisation of the Rafael resource, Buru’s integrated energy subsidiaries also continue
to make good progress towards generating value in the energy expansion (via natural hydrogen
and helium exploration) and energy transition (via Carbon Capture and Storage) areas.
I would like to thank our shareholders as well as new institutional investors for their trust and
confidence in the Company. The success of the recent Share Placement and oversubscribed
Share Purchase Plan is a strong endorsement of our belief in the Company’s future. As we move
forward, we remain focused on our strategic objectives and are committed to delivering
sustainable growth and value for all stakeholders.”
Thomas Nador, Chief Executive Officer
1
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Highlights
Exploration and Appraisal
•
Initial review of the fast-tracked processing volume of the Rafael 3D Seismic Survey
was completed and showed material data quality improvement over the vintage 2D data,
reconfirming the potential of the significant Rafael conventional gas and condensate
resource.
Early interpretation insights from the wider 3D data set outside the Rafael structure also
showed encouraging prospectivity including areas that were not apparent on the vintage
data. These areas have the potential to provide material backfill opportunities to a
Rafael development as well as other commercialisation options.
•
Pre-Front End Engineering Design study was awarded to GHD Pty Ltd (GHD) for the
Rafael gas condensate resource Phase 1 development. GHD will deliver concept select
level engineering for the first phase of the Rafael development in 1H CY2024, enabling
the project’s progression to Front End Engineering Design in 2H CY 2024.
•
2024 Rafael Appraisal Drilling long lead well equipment items including casing,
casing accessories and wellheads were ordered to ensure the planned appraisal drilling
schedule for 2H CY2024 is maintained.
•
Miro Capital was appointed as corporate advisor to assist with Buru’s Strategic Partner
Selection Process for the appraisal and development of its 100% owned Rafael
conventional gas and condensate resource in Western Australia’s Canning Basin.
Integrated Energy Projects (via wholly owned subsidiaries of Buru)
•
Buru’s wholly owned hydrogen and helium business 2H Resources successfully applied
for six Special Prospecting Authorities with Acreage Option (SPA-AO’s) under the
Petroleum and Geothermal Energy Resources Act 1967 (PGERA) in Western Australia.
These applications were accepted by the Department of Energy, Mines, Industry
Resources and Safety (DEMIRS) in accordance with the PGERA as being valid and are
under assessment.
•
GeoVault, Buru’s wholly owned CCS focused subsidiary completed an independently
validated geological greenhouse gas (GHG) storage potential assessment for areas in
and around Buru’s petroleum permits and licences in the Canning Basin.
This work confirmed that the storage capacity for GeoVault’s defined areas significantly
exceeds the estimated Scope 1 and Scope 2 CO2 emissions from the proposed Rafael
conventional gas and condensate hub scale development, providing further confidence
in the commercialisation pathway for a larger scale, CCS enabled development.
Corporate
•
Buru successfully completed a Share Placement with several of Buru’s major
shareholders as well as new institutional shareholders raising a total of some $5 million.
A Share Purchase Plan was also launched in November 2023 and closed on 8 December
raising a further $3.7 million.
2
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Figure 1 – Operational areas in the Canning Basin
3
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
(for reference)
Figure 2 – 2H Resources Exploration Licence application areas in South Australia
Figure 3 - 2H Resources Western Australian application areas
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
4
Appraisal Program for the Rafael Gas and Condensate Discovery
The low impact Rafael 3D seismic survey acquisition was completed on 29 September 2023,
on schedule and on budget, under the detailed supervision of the traditional owners of the
area in which the survey was undertaken. Survey data was harvested and exported for
processing on 11 October 2023.
The fast-tracked data processing was undertaken by RealTime Seismic (RTS) in Australia and
in France and was subject of initial review Buru’s inhouse geoscience team.
A second seismic processing contractor, Earth Signal Processing Ltd (Earth Signal) in Canada
has been processing the Rafael 3D seismic data in parallel with the fast-tracked processing
effort and will deliver final processed products to Buru by the end of February 2024, which
will enable detailed interpretation of the full 3D volume.
The Earth Signal processing will apply more detailed and sophisticated techniques that are
more time and resource intensive. This additional volume will facilitate a detailed
interpretation of the Rafael structure and the geometry and stratigraphy of the Rafael gas
and condensate reservoirs and will assist in Rafael appraisal well planning. It will also be a
key driver of future hydrocarbon exploration activities in the region.
Key Early Insights
The fast-tracked processing and interpretation of the Rafael 3D seismic data has confirmed
three significant early insights:
•
There is a significant data quality uplift from the vintage 2D seismic survey which was
acquired in 2013 (Refer Figure 4). The gas bearing Dolomite reservoirs and the sealing
Laurel Shale are clearly visible and can be confidently mapped across the structure on
this data volume. The high-quality data from the Earth Signal processing will further
assist in the detailed interpretation of the Rafael reservoir packages to provide further
confidence in potential resource volumes and appraisal drilling locations,
•
The initial review of the fast-track volume has confirmed the areal extent of the Rafael
structure remains consistent with previous interpretations, thereby reconfirming the
potential of a significant conventional gas and condensate resource, and
•
Initial review confirms the encouraging exploration prospectivity in the area, including
at the previously identified Salinas and Udialla prospects, and continues to build a
staircase of sizeable prospects and leads within tie-back distance to Rafael.
5
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Rafael 1 – Vintage 2D Seismic (2013)
Rafael 1 – Fast-track 3D Seismic (2023)
Figure 4- Significant 3D data quality uplift from vintage 2D seismic survey.
To maintain the planned 2024 Appraisal Drilling schedule, Buru placed well equipment long
lead item orders during the quarter.
These included orders with Marubeni-Itochu Tubulars Oceania Pty Ltd for casing, with Cactus
Wellheads Australia for wellhead and XMT tree, as well as with R&D Solutions for casing
accessories to support the drilling of an appraisal well, and the recompletion and test of the
Rafael 1 well, planned for the Kimberley field operating season in the second half of 2024.
Detailed well design has progressed and discussions with potential rig providers continued
during the quarter.
Commercialisation of the Rafael Gas and Condensate Discovery
During the quarter Buru awarded GHD Pty Ltd (GHD) the pre-Front End Engineering Design
(pre-FEED) scope for the Rafael Phase 1 development. This followed the Company’s
confirmation of a two-phase development strategy announced in August 2023 to
commercialise its 100% owned Rafael discovery – the first proven significant conventional
gas and condensate field in the Canning Basin of Western Australia.
The engineering concept for the Rafael Phase 1 development (Figure 5) includes a small
footprint, scalable, Kimberley based hybrid gas to power and renewables project based on
the already defined low volume estimate of the Rafael contingent resource1. This project is
designed to meet the forecast energy needs of the Kimberley, significantly reducing the
reliance of imported LNG and diesel fuel to support electricity generation and the broader
energy needs of the region.
Pre-FEED engineering for this first phase development is expected to be completed in 1H
CY2024, enabling the progression of the project to FEED in early 2H CY2024, Final
Investment Decision in 2H 2025 and first production in 2H CY2027.
1 Refer to ASX release of 26 April 2022 and 13 February 2023 for full definitions and disclosures. Buru is not
aware of any new information or data that materially affects this assessment and that all material assumptions
and technical parameters underpinning the estimates continue to apply and have not materially changed.
6
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Figure 5 - Rafael Phase 1 Development Concept
The timing of concept selection and pre-FEED engineering for a larger scale Rafael Phase 2
development will be informed by the results of appraisal drilling planned for 2H CY2024 and
will be based on mid to high resource volume estimates of Rafael contingent resources.
Feasibility studies have been completed for Carbon Capture and Storage (CCS) enabled
ammonia or methanol production concepts (0.5 – 1.0 MTPA), and a concept for a 1.6MTPA
LNG production facility targeting the export LNG market.
Opportunity Delivery Plan
Phasing the Rafael development will deliver numerous benefits including early cashflows to
Buru and reduced capital expenditure to reach first production and cashflows. Phasing the
development will also facilitate a wider range of project financing options (including access
to government grants and incentives), and an overall improved funding position for Buru.
Figure 6 describes the high-level activities for a sequenced development of the Rafael
resource.
7
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Figure 6 – High level development timeline
Timeline is indicative and is subject to capital availability, future discussions with potential asset
partners, offtake arrangements, land access and regulatory approvals.
Canning Basin Partner Selection Process
In October 2023 Buru appointed Miro Capital (Miro) to act as advisor to the Company in its
current strategic partner selection process for the Rafael gas condensate resource and its
other interests in the Canning Basin.
The process is advancing to schedule, with Australian and International parties participating
in due diligence activities. The results of final Rafael 3D seismic survey products are key
inputs to this process, and as such the process is not expected to be finalised until 2Q
CY2024.
Ungani Oilfield (L20/L21 - Buru 100%)
Operations at the Ungani Production facility were suspended on 27 August 2023 following
the removal of the temporary dual lane causeway that was used by Buru to transport Ungani
crude oil across the Fitzroy River. A subsequent risk assessment determined that a temporary
replacement barge facility proposed by Government at the time would not be suitable for the
safe and reliable transportation of crude oil via road trains across the Fitzroy River prior to
the construction of a permanent river crossing.
The suspension involved the orderly and staged termination of key contract arrangements
associated with the trucking and storage of Ungani crude oil, as well as employment contracts
with Ungani operations personnel to significantly and appropriately reduce fixed and monthly
operating costs.
8
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
In December 2023 a new permanent bridge across the Fitzroy River was opened six months
ahead of schedule, and Buru is currently exploring various technical and commercial options
for the future of the Ungani Oilfield.
Other Oil and Gas Assets
Yulleroo Gasfield (Within EP 391 & EP 436 – Buru 100%)
The Yulleroo Gasfield accumulation contains a substantial 2C tight gas resource of over 700
bcf that has been independently certified. It forms part of the much larger prospective tight
gas resource in the wider Canning Basin and has potential for conventional gas resources.
Further analysis of the potential for a well targeting conventional sands in the accumulation
continues to be undertaken as part of the planning for future drilling campaigns in the Basin.
Lennard Shelf including Blina Oilfield (L6 & L8 – Buru 100%)
Decommissioning of the legacy Lennard Shelf assets continued during the quarter. Any future
production from Lennard Shelf fields including the Blina Oilfield and any new discoveries will
require installation of new equipment meeting current regulatory and environmental
standards.
Integrated Energy Projects
Buru continues to develop three energy expansion and energy transition focused businesses
via its wholly owned subsidiary companies 2H Resources (natural hydrogen and helium
exploration and development), GeoVault (Carbon Capture and Storage) and Battmin (battery
minerals exploration.)
Balancing its short-medium term returns via its hydrocarbon focused business with its
longer-term business drivers and licence to operate, Buru is carrying out work both through
internal Buru Energy activity and through these subsidiaries, with the objective of these
subsidiaries becoming independent entities at an appropriate time.
Natural hydrogen exploration and development – 2H Resources
2H Resources was established to apply the geological knowledge of its supporting
shareholder Buru Energy in the exploration and appraisal of natural hydrogen (White or Gold
Hydrogen) accumulations. If found in commercially exploitable quantities, natural hydrogen
will be cost competitive against all forms of industrially manufactured hydrogen and could
potentially support the energy transition as a low to no-carbon energy source.
2H Resources has established an exploration portfolio in South Australia where the regulatory
framework is in place for natural hydrogen exploration and is actively evaluating other areas
where there is potential for natural hydrogen occurrences.
2H Resources has been confirmed as the preferred applicant for the granting of six South
Australian Petroleum Exploration Licences for hydrogen exploration that are geologically on
trend with legacy hydrogen discoveries, and two Gas Storage Exploration Licences.
An independent third-party Hydrogen Prospective Resource estimate from RISC Advisory for
these Petroleum Exploration Licence applications has confirmed the very significant potential
of these areas (Refer to ASX release of 23 January 2023) which reinforces 2H Resources’
view of the value opportunity associated with this venture.
9
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
The granting of the hydrogen exploration and gas storage licences to 2H Resources is subject
to the completion of land access agreements in accordance with the requirements of the
Commonwealth Native Title Act 1993 over any area where Native Title interests exist.
During the quarter:
•
2H Resources applied for six Special Prospecting Authorities with Acreage Option (SPAAO’s) under the Petroleum and Geothermal Energy Resources Act 1967 (PGERA) in
Western Australia. These applications have been accepted by the Department of Energy,
Mines, Industry Resources and Safety (DEMIRS) in accordance with the PGERA as being
valid and are under assessment. These applications are the result of extensive geological
research undertaken by the 2H Resources technical team and follow the removal of the
reservation on SPA-AO’s imposed by the Western Australian Government between 2021
and 2023.
•
Four of these SPA-AO’s are at 75% equity in partnership with Gehyra Flux Pty Ltd
(Gehyra Flux) in an area covering ~20,000km² northwest of Perth adjacent to the
margins of the Perth Basin where geological conditions are interpreted to be favourable
for generation of helium and associated gases.
•
A further two SPA-AO’s (at 100% equity) are situated in the Goldfields area between
Norseman and Kalgoorlie. These Goldfields areas are close to infrastructure and access
to market and have optimal geological characteristics for the generation of helium and
importantly have had previous strong indications of natural gas influxes during mineral
drilling activity.
•
Upon the completion of the Assessment stage which includes Native Title negotiations
and granting of the SPA-AO, 2H Resources will have six months to undertake a soil gas
sampling program which will seek to identify areas of anomalously high gas flux which
will then be high-graded for future exploration.
Carbon Capture and Storage (CCS) – GeoVault
Carbon capture and storage (CCS) is the process of capturing carbon dioxide (CO2) before
it enters the atmosphere, transporting it, and storing it in underground geological formations.
CCS complements other emission reduction technologies by addressing emissions that
currently cannot be avoided, including CO2 emissions from industrial processes.
Since early 2021 Buru has been progressing CCS technical and commercial activities through
its GeoVault subsidiary, with a focus on onshore geological greenhouse gas (GHG) storage.
GeoVault aims to be a pre-eminent operator in the identification, development and operation
of GHG storage projects in Australia. Leveraging Buru’s considerable geological intellectual
property, GeoVault is in the process of building a GeoVault-operated inventory of geologically
suitable storage formations matched to projects requiring storage.
In addition to providing direct benefits to Buru and its Rafael development, this storage
capacity will be made available to companies seeking to reduce their GHG emissions as part
of the transition to a lower carbon future.
During the quarter:
•
The in-house GeoVault team completed an assessment of the geological greenhouse gas
(GHG) storage potential for areas in and around Buru’s petroleum licences and permits
that has been independently validated by RISC Advisory.
10
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
•
This assessment is in support of the commercialisation pathway for Buru’s 100% owned,
low reservoir CO2 Rafael conventional gas and condensate discovery in the onshore
Canning Basin of Western Australia.
•
The independently reviewed CO2 storage estimates prepared by GeoVault for these
areas confirmed material hub scale CCS potential, that significantly exceeds the
estimated source CO2 emissions from a larger-scale Rafael project, thus providing a
pathway to potentially significant reductions in Scope 1 and Scope 2 emissions from the
planned project.
Battery Minerals Exploration - Battmin (Buru 50%, Sipa Resources 50% and Operator)
Battmin, a wholly owned subsidiary of Buru, was initially formed to apply the geological
knowledge that Buru had acquired in its extensive petroleum exploration activity in the
Canning Basin to the exploration for minerals formed by similar processes, and often in
association with, oil and gas accumulations.
Battmin’s activities remain focused on its Barbwire Terrace demonstration project in the
central Canning Basin in joint venture with Sipa Resources Limited (“Sipa”), where the JV is
targeting zinc/lead mineralisation in carbonate sections along a Devonian Reef Trend.
During the quarter, the Joint Venture continued work on the core analysis from the three
diamond core holes drilled late 2022 and worked to define any future potential activity on
this project.
Corporate
On 14 November 2023 Buru successfully completed a Share Placement with a number of
Buru’s major shareholders as well as new institutional shareholders raising a total of some
$5 million. A Share Purchase Plan was also launched in November 2023 and closed on 8
December raising a further $3.7 million.
The funds will be used to ensure that preparations for the planned 2024 appraisal drilling
program maintain their current momentum and the Company is fully funded through its
current program of partner selection and commercialisation activity. The total number of new
shares issued by way of the Share Placement and Share Purchase Plan was some 75.3
million.
11
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Financial
As at 31 December 2023, the Company had ~$18.4 million in cash and cash equivalents,
with no debt. The ASX Appendix 5B attached to this report contains the Company’s cash flow
statement for the quarter which is summarised as follows:
Cashflows
Opening cash
Production (net)
Development
Exploration
Corporate & Admin (net of interest income)
Proceeds from sale of Carnarvon Basin permit
Proceeds from issues of equity (net of costs)
Total cash inflow / (outflow)
Closing cash
December 2023
Quarter
$9.5m
$3.6m
($2.3m)
($0.9m)
$8.5m
$8.9m
$18.4m
Year to date 2023
$17.9m
($0.1m)
($10.2m)
($2.7m)
$5.0m
$8.5m
$0.5m
$18.4m
Production:
Cash sale proceeds from the August 2023 lifting were
received in early October 2023. The Ungani Production
Facility is now under care and maintenance.
Exploration:
Exploration cash outflows are mainly attributed to the
appraisal activities associated with the Rafael 3D
Seismic Acquisition. As part of Origin’s withdrawal from
the Canning Basin, Origin is funding up to A$4 million
of the survey costs. Other costs incurred relate to asset
integrity and decommissioning costs, expenditures
relating to desktop geological and geophysical work, as
well as integrated energy transition projects and other
new ventures.
Corporate and Admin:
Corporate and admin cash outflows were consistent
with the prior quarters. Buru continues to focus on
capital allocation discipline and cost control. As
outlined in the attached Appendix 5B (section 6.1),
$138,000 in payments were made to related parties
for directors’ fees.
Proceeds from Issue of Equity: Proceeds (net of costs) of $8.5M were received during
the quarter following a Share Placement and Share
Purchase Plan which resulted in the issuance of some
75.3 million new shares.
12
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
This ASX announcement has been authorised for release by the Buru Board of Directors.
For further information, visit www.buruenergy.com or contact
Thomas Nador, Chief Executive Officer
Telephone: +61 8 9215 1800
Freecall:
1800 337 330
Email:
info@buruenergy.com
13
Level 2, 16 Ord St West Perth WA 6005
1800 337 330
info@buruenergy.com
ABN 71 130 651 437
Schedule of interests in permits as at 31 December 2023
Permit
L61
L8
L 17
L 20
L 21
EP 129 1
EP 391
EP 428
EP 431
EP 436
EP 457
EP 458
E04/2674
E04/2684
1
Type
Production licence
Production licence
Production licence
Production licence
Production licence
Exploration permit
Exploration permit
Exploration permit
Exploration permit
Exploration permit
Exploration permit
Exploration permit
Exploration permit
Exploration permit
Ownership
Operator
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
60.00%
60.00%
50.00%
50.00%
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Energy Ltd
Buru Fitzroy Pty Ltd
Buru Fitzroy Pty Ltd
Sipa Resources Pty Ltd
Sipa Resources Pty Ltd
Location
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Canning Basin, WA
Buru’s interest in L6 and EP 129 exclude the Backreef Area
About Buru Energy
Buru Energy Limited (ASX: BRU) is a Western Australian energy company headquartered in Perth with an operational office in
Broome. The Company’s goal is to deliver material benefits to its shareholders, the State of Western Australia, the Traditional
Owners and communities of the areas in which it operates, by successfully exploring for and developing petroleum resources
and by contributing to driving the energy transition in an environmentally and culturally sensitive manner.
The Company’s petroleum assets and tenements are located onshore in the Canning Basin in the southwest Kimberley region
of Western Australia. In the Kimberley it owns and operates 100% of the conventional Ungani Oilfield project and the
conventional gas condensate discovery at Rafael 1. It also operates a Canning Basin wide portfolio of exploration permits and
licences prospective for conventional and unconventional resources with working interests ranging from 60% to 100%.
Buru Energy is also participating in the new energy economy through its subsidiary companies’ activities in natural hydrogen
and helium, carbon capture and storage, and battery minerals.
Forward Looking Statements
This document has been prepared by Buru Energy Limited ABN 71 130 651 437 (“Buru Energy"). This report contains certain
statements which may constitute "forward-looking statements". It is believed that the expectations reflected in these
statements are reasonable but they may be affected by a variety of variables and changes in underlying assumptions which
could cause actual results or trends to differ materially, including, but not limited to: price fluctuations, actual demand, currency
fluctuations, drilling and production results, reserve and resource estimates, loss of market, industry competition,
environmental risks, physical risks, legislative, fiscal and regulatory developments, economic and financial market conditions
in various countries and regions, political risks, project delays or advancements, approvals and cost estimates. All of Buru’s
operations and activities are subject to joint venture, regulatory and other approvals and their timing and order may also be
affected by weather, availability of equipment and materials and land access arrangements, including native title arrangements.
Although Buru believes that the expectations raised in this report are reasonable there can be no certainty that the events or
operations described in this report will occur in the timeframe or order presented or at all.
There are numerous uncertainties inherent in estimating reserves and resources, and in projecting future production,
development expenditures, operating expenses and cash flows. Oil and gas reserve engineering and resource assessment must
be recognised as a subjective process of estimating subsurface accumulations of oil and gas that cannot be measured in an
exact way. Any contingent resources and prospective resources presented in this report are pursuant to the Company’s ASX
releases of 18 January 2018 and 26 April 2022. The estimates of contingent and prospective resources included in this
Presentation have been prepared in accordance with the definitions and guidelines set forth in the SPE PRMS. Buru Energy is
not aware of any new information or data that materially affects the information included in this presentation and all material
assumptions and technical parameters underpinning the estimates in this presentation continue to apply and have not materially
changed. The probabilistic method was used to prepare the estimates of the contingent and prospective resources.
No representation or warranty, expressed or implied, is made by Buru or any other person that the material contained in this
report will be achieved or prove to be correct. Except for statutory liability which cannot be excluded, each of Buru, its officers,
employees and advisers expressly disclaims any responsibility for the accuracy or completeness of the material contained in
this report and excludes all liability whatsoever (including in negligence) for any loss or damage which may be suffered by any
person as a consequence if any information in this report or any error or omission there from. Neither Buru nor any other
person accepts any responsibility to update any person regarding
Share your feedback